Sprint Velocity report
Sprint Velocity report – User guide
The Sprint Velocity report helps you compare how much work your team commits to a sprint and how much it actually completes.
Open the Sprint Velocity report
In Jira, open Report Builder.
Click Create report.
From the list of templates, select Sprint velocity.
You’ll see:
The Configure panel on the left.
The Sprint Velocity chart in the center.
The Report data table at the bottom.
Configure the report
Use the Configure panel on the left.
Select project to display
Select project to display
Choose the Jira project whose sprints you want to analyze
(e.g. Report Builder (RB)).
Only sprints from this project will be used.
What to calculate
What to calculate?
Select the metric for the velocity, for example:Issue count– compares how many issues were committed vs completed.
Tip: Pick the same metric you use for sprint planning (issues, story points, etc.).
Choose which sprints to show
Last closed sprints to display
Enter how many of the most recent closed sprints you want to see
(e.g.5).
Optional checkboxes:
Show all closed sprints – ignore the number above and show every closed sprint.
Show all active sprints – also include sprints that are currently in progress.
Show all future sprints – include planned sprints.
Use these to switch between a short recent history and a full backlog of sprints.
Additional display options
Show completed average
Adds a black line showing the average completed value across all visible sprints.
Show trending line
Adds a blue line showing the trend of completed work over time.
Show result table
Shows/hides the Report data table under the chart (Sprint / Committed / Completed).
Show sources table
Shows/hides the technical sources table with details about the underlying data.
The chart updates automatically when you change any option.
Understanding the chart
In the Sprint Velocity chart:
Gray bars – Committed
Amount of work planned at the start of the sprint.Green bars – Completed
Amount of work actually finished by the end of the sprint.Black line – Completed average (optional)
Average completed value across all visible sprints.Blue line – Trending (optional)
Trend of completed work over time.
Hover a bar or a line point to see exact values.
Report data table
The Report data section under the chart shows exact numbers.
Columns:
Sprint – Sprint name (e.g.
RB. Sprint 19).Committed – Planned work at sprint start.
Completed – Work finished by sprint end.
Use this table for quick checks or export.
How to use this report
Typical use cases:
Detect over-commitment
Gray bars consistently higher than green bars.
Check stability of delivery
Green bars fluctuating around the black average line.
Measure impact of process changes
Blue trend line going up or down after changes.
Use historical completed values for future sprint planning.